张家港浦沙码头至张家港海力#2码头前沿水域大件吊装作业航行通告
发布日期:2022-09-07 14:39 浏览次数:

@font-face{ font-family:"Times New Roman"; } @font-face{ font-family:"宋体"; } @font-face{ font-family:"仿宋_GB2312"; } @font-face{ font-family:"方正小标宋简体"; } @font-face{ font-family:"方正黑体_GBK"; } p.MsoNormal{ mso-style-name:正文; mso-style-parent:""; margin:0pt; margin-bottom:.0001pt; mso-pagination:none; text-align:justify; text-justify:inter-ideograph; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:16.0000pt; mso-font-kerning:1.0000pt; } p.MsoFooter{ mso-style-name:页脚; margin:0pt; margin-bottom:.0001pt; layout-grid-mode:char; mso-pagination:none; text-align:left; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:9.0000pt; mso-font-kerning:1.0000pt; } p.MsoHeader{ mso-style-name:页眉; margin:0pt; margin-bottom:.0001pt; border-bottom:1.0000pt solid windowtext; mso-border-bottom-alt:0.7500pt solid windowtext; padding:0pt 0pt 1pt 0pt ; layout-grid-mode:char; mso-pagination:none; text-align:center; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:9.0000pt; mso-font-kerning:1.0000pt; } span.msoIns{ mso-style-type:export-only; mso-style-name:""; text-decoration:underline; text-underline:single; color:blue; } span.msoDel{ mso-style-type:export-only; mso-style-name:""; text-decoration:line-through; color:red; } @page{mso-page-border-surround-header:no; mso-page-border-surround-footer:no;}@page Section0{ } div.Section0{page:Section0;}

张家港浦沙码头至张家港海力#2码头

前沿水域大件吊装作业航行通告

 

各有关单位、船舶

上海三航奔腾海洋工程限公司将在张家港浦沙码头至张家港海力#2码头前沿进行大件吊装作业,有关事项通告如下

一、作业时间 

202297日至98日,每日0600时至1800时。

二、作业水域

长江浏海沙水道长江#42红浮南侧张家港浦沙码头至张家港海力#2码头前沿长(东西)600米、宽(南北)200米的水域范围内。

三、作业船舶

秦航工88(起重船,船长68.4米,船宽27.2米)

秦航工拖3001(拖船,辅助作业船);

秦航工拖1001(拖船,辅助作业船)。

四、作业方式

起重船字形停泊在张家港浦沙码头前沿起吊门机然后通过绞缆和拖轮协助移泊至张家港海力#2码头前沿卸载。起重船船艏在码头上带“八”字缆,船艉抛“八”字锚,锚间距约600米,距码头前沿约200米 

五、注意事项

(一)码头单位应督促作业单位严格按照施工通航安全保障方案进行作业,落实各项安全保障和防污染措施。

(二)作业船舶应严格遵守《长江江苏段船舶定线制规定(2021)》和其他相关的法律规定,在核定范围内作业,按规定显示信号,加强值班和警戒,开启AIS,保持甚高频值守,主动发布信息。

(三)吊装作业时,作业船舶按规定显示相关信号,安排专人守听VHF06频道,主动加强与拟通过该区域船舶的联系,必要时暂停作业,采取避让措施。

(四)作业期间,所有航经该附近水域的船舶应保持高频守听,加强望,谨慎操作,与作业船舶保持安全距离,并服从张家港海事局水上交通管理中心的交通组织。

(五)如遇雷暴大风等恶劣天气情况,船舶应停止作业,落实各项安全和应急处置措施。

作业结束后,不再另行通告。

 

 

 

张家港海事局

 

2022年9月7日


编辑:(张家港海事局
信息来源:张家港局
关闭
打印
上一篇:
下一篇:
张家港浦沙码头至张家港海力#2码头前沿水域大件吊装作业航行通告

来源:张家港局    时间:2022-09-07 14:39

@font-face{ font-family:"Times New Roman"; } @font-face{ font-family:"宋体"; } @font-face{ font-family:"仿宋_GB2312"; } @font-face{ font-family:"方正小标宋简体"; } @font-face{ font-family:"方正黑体_GBK"; } p.MsoNormal{ mso-style-name:正文; mso-style-parent:""; margin:0pt; margin-bottom:.0001pt; mso-pagination:none; text-align:justify; text-justify:inter-ideograph; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:16.0000pt; mso-font-kerning:1.0000pt; } p.MsoFooter{ mso-style-name:页脚; margin:0pt; margin-bottom:.0001pt; layout-grid-mode:char; mso-pagination:none; text-align:left; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:9.0000pt; mso-font-kerning:1.0000pt; } p.MsoHeader{ mso-style-name:页眉; margin:0pt; margin-bottom:.0001pt; border-bottom:1.0000pt solid windowtext; mso-border-bottom-alt:0.7500pt solid windowtext; padding:0pt 0pt 1pt 0pt ; layout-grid-mode:char; mso-pagination:none; text-align:center; font-family:'Times New Roman'; mso-fareast-font-family:仿宋_GB2312; font-size:9.0000pt; mso-font-kerning:1.0000pt; } span.msoIns{ mso-style-type:export-only; mso-style-name:""; text-decoration:underline; text-underline:single; color:blue; } span.msoDel{ mso-style-type:export-only; mso-style-name:""; text-decoration:line-through; color:red; } @page{mso-page-border-surround-header:no; mso-page-border-surround-footer:no;}@page Section0{ } div.Section0{page:Section0;}

张家港浦沙码头至张家港海力#2码头

前沿水域大件吊装作业航行通告

 

各有关单位、船舶

上海三航奔腾海洋工程限公司将在张家港浦沙码头至张家港海力#2码头前沿进行大件吊装作业,有关事项通告如下

一、作业时间 

202297日至98日,每日0600时至1800时。

二、作业水域

长江浏海沙水道长江#42红浮南侧张家港浦沙码头至张家港海力#2码头前沿长(东西)600米、宽(南北)200米的水域范围内。

三、作业船舶

秦航工88(起重船,船长68.4米,船宽27.2米)

秦航工拖3001(拖船,辅助作业船);

秦航工拖1001(拖船,辅助作业船)。

四、作业方式

起重船字形停泊在张家港浦沙码头前沿起吊门机然后通过绞缆和拖轮协助移泊至张家港海力#2码头前沿卸载。起重船船艏在码头上带“八”字缆,船艉抛“八”字锚,锚间距约600米,距码头前沿约200米 

五、注意事项

(一)码头单位应督促作业单位严格按照施工通航安全保障方案进行作业,落实各项安全保障和防污染措施。

(二)作业船舶应严格遵守《长江江苏段船舶定线制规定(2021)》和其他相关的法律规定,在核定范围内作业,按规定显示信号,加强值班和警戒,开启AIS,保持甚高频值守,主动发布信息。

(三)吊装作业时,作业船舶按规定显示相关信号,安排专人守听VHF06频道,主动加强与拟通过该区域船舶的联系,必要时暂停作业,采取避让措施。

(四)作业期间,所有航经该附近水域的船舶应保持高频守听,加强望,谨慎操作,与作业船舶保持安全距离,并服从张家港海事局水上交通管理中心的交通组织。

(五)如遇雷暴大风等恶劣天气情况,船舶应停止作业,落实各项安全和应急处置措施。

作业结束后,不再另行通告。

 

 

 

张家港海事局

 

2022年9月7日